Eaves and verges detail for a plain clay roof

 

eaves with over fascia ventilation

Eaves with over fascia ventilation

Set top of fascia board at correct level and fit ventilator in accordance with  Manufacturers Recommendations. Eaves courses of tiles should be at same pitch as general tiling. If a sprocketted or bell-cast detail is used, then eaves courses should be no lower than the minimum recommended roof pitch (35 degrees).
Fix a plywood board or proprietary tray to provide continuous support to underlay to prevent water retaining troughs.
Fix a rafter spacer tray to provide a clear air path between underlay and insulation.

Download dwg file

Download jpg file

Download dxf file

 

 

 

 

 

eaves with soffit ventilationEaves with Soffit Ventilation

Set top of fascia board at correct level. Eaves courses of tiles should be at same pitch as general tiling. If a sprocketted or bell-cast detail is used, then eaves courses should be no lower than the minimum recommended roof pitch (35 degrees).
Fix a plywood board or proprietary tray to provide continuous support to underlay to prevent water retaining troughs.
Fix a rafter spacer tray to provide a clear air path between underlay and insulation.

Download dwg file

Download jpg file

Download dxf file

 

 

 

 

open eaves with ventilating rafter trayOpen Eaves with ventilating rafter tray

Fix timber fillet to set eaves courses of tiles at same pitch as general tiling. If a sprocketted or bell-cast detail is used, then eaves courses should be no lower than the minimum recommended roof pitch.
Fix a screen to prevent ingress of birds, rodents and large insects etc, or use proprietary rafter spacer tray with integral screen to provide a clear air path between underlay and insulation.

Download dwg file

Download jpg file

Download dxf file

 

 

 

 

Bedded verge

Bedded Verge

Carry underlay 50mm onto outer leaf of gable wall.  Bed an undercloak of plain tiles laid face down with bottom ends exposed, projecting not more than 50mm beyond face of wall.
Carry tiling battens over undercloak and finish 100mm from verge edge.
Fix standard tiles and tile-and-a-half tiles in alternate courses.
Bed edge of verge tiles flush with undercloak on 75mm wide bed of mortar leaving the edges clean.

Download the dwg file

Download jpg file

Download dxf file

 

 

 

 

 

cloaked verge version 2

 

Cloaked verge

Carry underlay over full width of gable wall and turn down 50mm behind cloaks.
Carry tiling battens over undercloak and finish flush with verge edge.
Fix cloaked verge tiles and standard tiles in alternate courses.
Note: Cloaked verge tiles are handed and should be specified when ordering.  Left hand verge is illustrated.

Download dwg file

Download jpg file

Download dxf file

Case Studies

Dreadnought Tiles is a company with an impeccable pedigree and it was a pleasure to see them continuing to thrive and innovate. Black Country craftmanship and quality at its best.” Andy Street, Mayor of the West Midlands

See More Testimonials >

View More Case Studies